OEE Calculations

Sample Excel

Basic OEE

  • Shift Length
  • Break Time
  • Planned Production Time === (Shift Length - Break Time)

  • Downtime
  • Runtime === ( Planned Production Time - Downtime)

  • Total Units
  • Rejected Units
  • Good Units === (Total Units - Rejected Units)

  • A (Run Time / Planned Production Time)
  • P (Total Units / Run Time) / Ideal Run Rate)
  • Q (Good Units / Total Units)

  • OEE === (A * P * Q)

OEE Losses

  • Cycle time === (Time to product 1 Unit)

  • Availability Losses === (Downtime / Cycle time) / (Total time / Cycle time)

  • Quality Losses === Rejected Units / (Total time / Cycle time)

  • Speed Losses === 100 - Availability losses - Quality losses - OEE