I'm using Redmine 2.3.2 + Better Gantt Chart 0.9.0.
When I'm creating Issues and linking one to follow another, the plugin is finding problems to dates next to weekends.
In the example above, we have #659 and #660.
The #659 finishes in a Friday.
The #660 is supposed to start on Monday.
When creating the relationship and setting that #660 follows #659 and clicking "add" the screen just blinks and no relationship is created.
I have to set a delay of 2 days (saturday and sunday) and then I am able to create the relationship without any problem.
See image bellow:
Do you have any clue or patch for this?
The text was updated successfully, but these errors were encountered:
I'm using Redmine 2.3.2 + Better Gantt Chart 0.9.0.
When I'm creating Issues and linking one to follow another, the plugin is finding problems to dates next to weekends.
In the example above, we have #659 and #660.
The #659 finishes in a Friday.
The #660 is supposed to start on Monday.
When creating the relationship and setting that #660 follows #659 and clicking "add" the screen just blinks and no relationship is created.
I have to set a delay of 2 days (saturday and sunday) and then I am able to create the relationship without any problem.
See image bellow:
Do you have any clue or patch for this?