Electricians snag list #108

Open
7 of 16 tasks
iteles opened this issue Jan 13, 2020 · 5 comments
Open
7 of 16 tasks

Electricians snag list #108

iteles opened this issue Jan 13, 2020 · 5 comments
Assignees

Comments

@iteles
Copy link
Member

iteles commented Jan 13, 2020

@iteles iteles self-assigned this Jan 13, 2020
@iteles iteles added the on-site label Jan 14, 2020
@iteles
Copy link
Member Author

iteles commented Jan 14, 2020

Electricians were in the house today, doing finishing touches. A lot of #47 (comment) was also completed today.

Will check list on-site tomorrow.

@iteles
Copy link
Member Author

iteles commented Mar 11, 2020

Last week and this week, our electricians were here finalising things and yesterday we had our 'vistoria' (electrical survey). Pending results.

@iteles
Copy link
Member Author

iteles commented Jul 3, 2020

Electrical inspection passed, onto increasing the electrical capacity next.
Leaving this issue open because there are still a number of snag list items to pursue (updated list in OP as well).

@iteles
Copy link
Member Author

iteles commented Oct 7, 2020

The electricians will be here on the 13-Oct-2020 to deal with #63 and will be digging into this list 👍

@iteles
Copy link
Member Author

iteles commented Oct 13, 2020

The electricians came today and it wasn't an entirely effective visit because the majority of the time they were here, there was no electricity (as they were here for #63).

But the following was done:

  • Supported the work done to increase the electrical capacity Electricity | Installing the BTE #63
  • Remove two lights from the bedrooms for swapping (one was no longer working and another was making a LOT of noise)
  • Put up the kitchen light we had swapped out to see if it makes less noise
  • Added the cable and wiring to the plumbing re-circ box Plumbing snag list #96
  • Hooked up the downstairs toilets taps to the electricity again
  • Installed one of the transformers on the urinol flushes BUT this doesn't work and will need to be reviewed - however, he's confident it's an electrical issue
  • Looked over the light we bought to try installing just outside the two back doors Varanda and external stairwell lighting #111 - this should work well but we might want one that's slightly less potent for the upstairs back door area because the one we have is super strong (ideal for downstairs which is really dark but quite blinding for upstairs)
    • To a certain extent, this is kind of what we want. We probably want to install the one we have downstairs first and then see what we do upstairs
  • Gave us keys to the BTE cupboard

There's one thing I'm bummed I forgot to ask him to do: remove the bottom light from the basement stairwell so we could get it swapped at the same time as the other two bedroom lights we're already taking in 🤦‍♀️

@iteles iteles mentioned this issue Nov 23, 2020
5 tasks
Sign up for free to join this conversation on GitHub. Already have an account? Sign in to comment
Projects
None yet
Development

No branches or pull requests

1 participant