This iteration's main goal will be to create the bare-bones of the whole project, a minimum viable product, meaning the creation of:
- User Dashboard
- Database Endpoints
- Renovation Project Page
- User framework including User Permissions
- Basic Chat System
With those feature in place, the client will be able to check the main functionality of the product, Managing Renovation Projects, and give initial feedback.
- The whole team
- Open Issues
- HuBoard - Visual Issues Board
- Renovation Project Page - 13 Points
- Basic Dashboard Page - 21 Points
- Basic Chat System - 13 Points
- Create Database Methods - 13 Points
Total: 60
Mid-Iteration Meeting:
- Completed Database methods - both frontend and backend
- Completed Basic chat system
- Completed Basic Dashboard page
The rest of the iteration will focus on:
- Polishing the Dashboard page and chat system
- Finishing the renovation page.
- Merging all the work and fixing resulting bugs.
- We completed all the iteration issues.
- Created Unit-Tests for both Frontend and Backend
Still need to fix remaining bugs and add additional functionality in the upcoming iterations.